Minimum time taken by each job to be completed given by a Directed Acyclic Graph
Pattern: Topological sort
Each job takes one unit of time and can start only after all jobs pointing to it are done. In topological order, a job finishes at 1 plus the latest finishing time among its prerequisites; jobs with none finish at time 1.
The problem
Jobs are numbered 1 to n; an edge [u, v] means job v can start only after job u ends. Every job takes one unit of
time and jobs without dependencies can run together. Return the earliest finishing time of each job.
Think first
- When does a job with no prerequisites finish?
- When does any other job finish?
- In what order can the times be computed?
Hints
Brute force, and why it fails
Repeatedly scan all jobs until no time changes: O(V × E).
The key insight
Processing jobs in topological order means every prerequisite's time is final when it is used.
Dry run
| time(1) | 1 |
|---|---|
| time(2) | 1 |
10 jobs; 1 and 2 have no prerequisites: time 1.
Step 1 of 3
The plan
Kahn; time[start jobs] = 1
when removing edge u → v: time[v] = max(time[v], time[u] + 1)
Complexity
- Time
O(V + E)- Space
O(V + E)
Kahn's algorithm once.
Edge cases
- No edges: every job 1.
- A chain: 1, 2, 3, ...
- Many prerequisites for one job.
I've built my logic, show the code
Java
import java.util.*;
class Solution {
public int[] minimumTime(int n, int[][] edges) { // jobs 1..n; edge {u, v}: v starts after u ends
List<List<Integer>> adj = new ArrayList<>();
for (int i = 0; i <= n; i++) adj.add(new ArrayList<>());
int[] indegree = new int[n + 1], time = new int[n + 1];
for (int[] e : edges) { adj.get(e[0]).add(e[1]); indegree[e[1]]++; }
Queue<Integer> q = new ArrayDeque<>();
for (int i = 1; i <= n; i++) if (indegree[i] == 0) { q.add(i); time[i] = 1; } // no prerequisite: done at time 1
while (!q.isEmpty()) { // in topological order, each job ends one unit after its last prerequisite
int u = q.poll();
for (int v : adj.get(u)) {
time[v] = Math.max(time[v], time[u] + 1);
if (--indegree[v] == 0) q.add(v);
}
}
return Arrays.copyOfRange(time, 1, n + 1);
}
}C++
class Solution {
public:
vector<int> minimumTime(int n, vector<vector<int>>& edges) { // jobs 1..n; edge {u, v}: v starts after u ends
vector<vector<int>> adj(n + 1);
vector<int> indegree(n + 1, 0), time(n + 1, 0);
for (const vector<int>& e : edges) { adj[e[0]].push_back(e[1]); indegree[e[1]]++; }
queue<int> q;
for (int i = 1; i <= n; i++) if (indegree[i] == 0) { q.push(i); time[i] = 1; } // no prerequisite: time 1
while (!q.empty()) { // in topological order, each job ends one unit after its last prerequisite
int u = q.front();
q.pop();
for (int v : adj[u]) {
time[v] = max(time[v], time[u] + 1);
if (--indegree[v] == 0) q.push(v);
}
}
return vector<int>(time.begin() + 1, time.end());
}
};Python
from collections import deque
class Solution:
def minimumTime(self, n: int, edges: list[list[int]]) -> list[int]: # jobs 1..n; [u, v]: v after u
adj, indegree, time = [[] for _ in range(n + 1)], [0] * (n + 1), [0] * (n + 1)
for u, v in edges:
adj[u].append(v)
indegree[v] += 1
q = deque(i for i in range(1, n + 1) if indegree[i] == 0)
for i in q:
time[i] = 1 # no prerequisite: done at time 1
while q: # in topological order, each job ends after its last prerequisite
u = q.popleft()
for v in adj[u]:
time[v] = max(time[v], time[u] + 1)
indegree[v] -= 1
if indegree[v] == 0:
q.append(v)
return time[1:]Common mistakes
- Adding times instead of taking the maximum.
- Using 0-based job numbers.